December 5, 2016
EDGE Innovate provide robust, safe & efficient shredding solutions to BCI
In 2000, representatives of the Canton of Jura and the BCI (an umbrella group for 8 Swiss chemical companies) signed an agreement to undertake the complete clear up of Europe’s largest toxic waste dump.
Shredding Hazardous Waste
Bonfol near the French border stopped receiving waste in 1976 after a 15-year period of service. A former clay pit it was used by the local chemical industries and the Swiss army to dump waste. It contains around 114,000 tonnes of chemical waste including solvents, colourants and even slightly radioactive material from the watch-making industry. In 1976 the dump was sealed and covered with foliage. However over time this clay bowl began filling up with water, causing contamination to spill out. From 1986-1995 extensive measures (drainage system, septic tank, and new cover) were taken to minimize the impact of the landfill on the environment.
In 2011, Basel Chemical Industry (BCI) of Switzerland placed and received an order of two full remote controlled EDGE slow speed shredders. The order had been placed after a local explosion occurred during a pilot project at the site in July 2010. Following the green light from the Minister of the Environment and Public Works of the Canton of Jura, Philippe Receveur, waste excavation work resumed on May 2011.
Previously facilities were tested with inert clay material. Now, the bridge crane grab excavates the discharge of waste and stores it in a tray. A remote-controlled excavator feeds the EDGE shredder that breaks waste and opens potential sealed. Finally, a remote-controlled trolley routes split wastes in the market preparation, where they are analysed, prepared and stabilized.
Fast track to 2016 and the two EDGE Slayers still play a pivotal role for BCI in land reclamation project. BCI needed a machine which could shred huge volumes of material which was both highly volatile and potentially explosive. Engineers from EDGE worked closely with BCI, to ensure optimum production while also minimizing the health and safety threat. The EDGE Slayers supplied to BCI have been fully customised to the operator’s unique specifications. The customised units supplied included full remote control functionality enabling an operator to have full control of the unit from a control room 100 meters away. To enabling loading from the radio remote excavator, EDGE customised the Slayer with a remote side tipping hopper. The EDGE Slayers have provided a key role in the safe rehabilitation of the contaminated site by processing the excavated waste, making it safe for incineration, eliminating the risks & damage from further potential explosions.
“This particular project is an extreme example of EDGE’s ability to offer customers a fully customised solution to ensure optimum production for their application. It demonstrates our willingness to work with our customers in this case, to ensure high production whilst ensuring we provided a solution that offered a high level of health safety”. Darragh Cullen EDGE Innovate, Managing Director.
With five years’ service in an unforgiving atmosphere the EDGE shredders are still operating as if new. A small weekly service is carried out with service personnel wearing protective suits. Oil and air filters are changed weekly due to high levels of dust and caustic air. “The shredders are alternated every 300 hours to enable more complex servicing to take place in a safe environment. The two large Liebherr diggers had to have engine changes after 1700 but the CAT engines found in the EDGE Slayers with the help of weekly air filter change are still running well”. Patrick Vallet, BCI Maintenance Engineer.
A total of 35,000 tonnes of waste has been excavated since April 2010 with the project planned to complete the final clean in 2016.
Mechanics: the challenge of the many constraints
The period of the hall of movement, among others, helped to review the large gear and facilities, as well as technical adaptations made necessary. Significant changes have been made for example on the two mills that crush the waste in the excavation hall.
“Because when the second stage of sanitation, the mill is positioned on the other side of the reception bunkers, we had to reverse many hydraulic, electrical and mechanical,” says Christophe Faivre, Garage boss Clos St-Ursanne. For example, the platform that powers the mill had to be changed aside: this is a steel bucket weighing a ton, 1.60 m of 2.00 m, with two hydraulic arms for a intensive use.
Following the explosion of July 2010, we had to find a way to reduce the size of waste agglomerates and open potential yet closed laboratory vessels. Alain Lachat, site manager of bci Betriebs-AG, had the idea of using a grinder, but still had to adapt the tracked machine 21 tons, 9.20 m long and 3 m high, with a power of 350 horses, the very specific needs of the site. He then turned to the Garage du Clos, a local company, which sells and fits of construction equipment.
“There were many constraints. So we dug the head with Mr. Lachat to meet this great challenge, “says Christophe Faivre. They have developed together the side platform that provides power to the mill at progressively by tilting. They duplicated the control panel of the mill so that it can be activated remotely from the control room. Connections were made to evacuate the exhaust gases of the hall. Do not forget: he had installed outside the hall a diesel tank that feeds the mill through a pipe located inside the hall.
After the first mill has demonstrated its efficiency, it was necessary to make the same adjustments on a second machine so that they are interchangeable. This redundancy ensures that sanitation is not blocked for days because of a malfunction. “To avoid blocking, we also prefabricated most important parts and we put up tent maintenance,” says C. Faivre. The mechanic Patrick Vallat regular service every week: check oil levels and coolant, hydraulic lines and the treadmill. It changes the air filter, grease joints and ensures that there are no anomalies.
Both mills are used alternately. Thus, every three months, the mill hall is exchanged, cleaned and subjected to a major overhaul. In this context, all the “teeth” steel fixed on the two rotors and that wear during waste crushing must be reconstituted by MIG. This procedure alone takes two weeks an experienced welder. “The Garage du Clos shows the seriousness and responsiveness necessary to ensure continuity of work,” Judge Alain Lachat of bci Betriebs-AG. We must ensure that in case of failure at any time, the mill of the hall can be quickly replaced.